Major projects
Pacific Link's 77-day window: keeping a clear record when consultation is compressed
An official note calls the Pacific Link consultation timeline compressed. What the dates show, what nations said, and what your record needs when time is short.
The short version
- Pre-listing consultation on the Pacific Link pipeline ran 77 days, from July 3 to September 18, 2026, with more than 130 communities on the list. Cabinet listed the project 13 days after the window closed.
- The explanatory note published with the Order in Council calls the timelines compressed, notes they fell during harvesting season and wildfires, and says the majority of Indigenous communities consulted were not prepared to support listing.
- Listing is not the end of consultation. The Act requires the Crown to consult again before it issues the conditions document, and a proposed law, not yet passed, would send challenges straight to the Federal Court of Appeal.
- When time is short, the record has to show requests and answers, capacity constraints, who actually engaged, and each nation's position in its own words.
The explanatory note published with the Order in Council that made Pacific Link Canada's first national interest project uses the word "compressed." It says the consultation timelines fell during harvesting season and wildfires. (The note is not part of the Order itself.) It also says that "the majority of Indigenous communities consulted were not prepared to support Project listing."
It is a candid account of the process, and a useful guide to what an engagement record needs to show when time is short. National interest projects are designed to move fast, and Pacific Link will not be the last one.
The dates, from the government's own record
News coverage described the consultation as two months long. The Order in Council gives exact dates, and they are the ones to rely on.
Alberta submitted the proposal to the federal Major Projects Office on July 2, 2026. Notification letters went out the next day, opening consultation with more than 130 communities. A notice appeared in the Canada Gazette on August 1. The original deadline for written submissions was August 26. It was extended to September 18 because of harvesting season and wildfires, and the office shared its preliminary national-interest assessment on August 28, with three weeks left to respond.
The window closed on September 18 after 77 days. Cabinet listed the project on October 1, 13 days later.
The project itself is large. The pipeline would run up to about 1,250 kilometres from Bruderheim, Alberta, to a deepwater port near Delta, BC, carrying a million barrels a day, at an estimated cost of $35.2 billion to $43.7 billion. Trans Mountain Corporation is the proponent for an ownership group that includes the Alberta Petroleum Marketing Commission and Pembina, and at least 10 per cent ownership is to be offered to Indigenous peoples.
The government's count of the engagement is in the same document: more than 140 meetings with more than 110 communities and organizations, 95 communities using participant funding, and more than 100 written submissions.
What nations said about the time
Coldwater Indian Band said its requests to extend consultation went unanswered while wildfire evacuations were under way (CFJC Today). Tsawwassen First Nation said in July that it had not been consulted (Daily Hive), and on the day of the listing said it would need to be adequately consulted on the marine terminal before taking a position (The Province).
Treaty 8 Grand Chief Trevor Mercredi sits on the Major Projects Office's Indigenous advisory council. He said the council was never asked whether the timeline was adequate, and that he would have said no (APTN News).
Cold Lake First Nations has gone to the Federal Court. It says it was left out of consultation on a project that affects its Treaty 6 rights, that the cumulative effects of oilsands growth were never addressed, and that the listing effectively approves a linked carbon capture project without consultation. It wants the designation quashed. Chief Kelsey Jacko put it simply: "We're trying to work with Canada. We keep trying, but nobody's trying with us." (APTN News)
Not every nation is opposed, and no nation has announced formal support. In the oilsands region, Fort McKay First Nation's chief has said the nation is interested in partnering, and Mikisew Cree First Nation's chief said the nation is neither endorsing nor opposing the project for now (CBC News). The most useful record captures this full range accurately.
Listing is not the end of consultation
The October 1 listing opens the next stage of consultation rather than closing it.
University of Calgary law professor David Wright explains on ABlawg that listing a project under the Building Canada Act deems the findings needed for its federal authorizations to be made in its favour, but the Crown still has to consult before it issues the single conditions document (s. 7(2)(c)). The duty to consult can't be deemed. In his words, "getting PLP on the Schedule 1 was the easy part." The government's target for those conditions is September 1, 2027.
The Order in Council is published in the Canada Gazette as P.C. 2026-925. A bill now before Parliament could make the early record even more important. Bill C-39, the proposed Building Canada Strong Act, would send challenges to national-interest orders straight to the Federal Court of Appeal. JFK Law's overview warns that consultation "will be compressed into fewer, earlier stages," so evidence has to go into the record during the short consultation window, because adding it later will be hard (JFK Law). The bill is before a Commons committee and is not law, and the Act's own consultation requirements remain as they are today.
Put those together and the conclusion for anyone keeping records is plain. On a fast-tracked project, the consultation-stage record may be the only record a reviewing body ever sees. This is general information, not legal advice.
What a clear record shows under compression
When time is short, a well-kept record does a lot of the work. For each nation, it shows:
- Every date that matters: notification, information sent, deadlines, and each extension request with its answer.
- Capacity constraints the nation raised, including wildfire evacuations, harvesting season and staffing, and what was done about each.
- Information the nation asked for, and whether and when it was provided.
- The difference between being on the consultation list and actually engaging. More than 130 communities were on the Pacific Link list; meetings were held with more than 110 communities and organizations. Those are different numbers for a reason.
- Participant funding offered and used.
- The nation's position in its own words, with a date and a source. "No position yet" is a valid entry.
- How the nation's concerns were considered, and the written answer it received.
In StakeholderHub, an unanswered request from a nation can be logged as an issue or a commitment with a due date, so it surfaces on the dashboard instead of sitting in someone's inbox. On a 77-day clock, that difference matters.
What to do this week
- On any file with a compressed schedule, build a dated list of every request a nation has made, for extensions, information or meetings, and the answer each one got.
- Record capacity constraints as part of the engagement record, not as background, along with what your team did in response.
- In every report, show "on the consultation list" and "engaged" as two separate numbers.
- If your project could become a national interest project, file evidence as you go. Assume the consultation-stage record is the one a reviewer will read.
Frequently asked questions
What is the Building Canada Act?
A federal law enacted through Bill C-5, the One Canadian Economy Act, which received royal assent on June 26, 2025. It lets the federal Cabinet list projects of national interest in Schedule 1. Listing deems the determinations, findings and opinions needed for the listed federal authorizations to be made in the project's favour (s. 6). The authorizations themselves are issued later in a single conditions document, and only after the Crown consults affected Indigenous peoples (s. 7). The Act also requires consultation before a project is listed (s. 5(7)).
How long was the Pacific Link consultation window?
According to the Order in Council listing the project, consultation ran from July 3 to September 18, 2026, which is 77 days. The deadline for written submissions was extended from August 26 to September 18 because of harvesting season and wildfires, and late submissions were still considered.
Does a national interest designation remove the Duty to Consult?
No. As University of Calgary law professor David Wright explains, the Building Canada Act requires the Crown to consult affected Indigenous peoples before it issues the conditions document for a listed project (s. 7(2)(c)), with a public report on that consultation within 60 days after the document is issued (s. 7(2.1)). In his analysis, the Duty to Consult cannot be deemed to have been met.
What is Bill C-39?
The proposed Building Canada Strong Act, introduced on September 21, 2026. It would amend the Impact Assessment Act, the Building Canada Act and the Canadian Energy Regulator Act, and send challenges to national-interest orders directly to the Federal Court of Appeal. Its main parts would take effect only by Cabinet order. As of October 24, 2026 it was before a House of Commons committee, a Senate committee was pre-studying it, and it was not law.
Sources
- Order in Council PC 2026-0925 and Explanatory Note (West Coast Oil Pipeline)Privy Council Office, Government of Canada · October 1, 2026
- Prime Minister Carney lists the West Coast Oil Pipeline, now known as Pacific Link, as a project of national interestPrime Minister of Canada · October 1, 2026
- Experimental deregulation: next steps for the Pacific Link pipeline as the first official Building Canada Act project of national interestABlawg (University of Calgary Faculty of Law) · October 5, 2026
- First Nations along Pacific Link pipeline denounce government over lack of consultationAPTN News · October 1, 2026
- 'There is anger in our community': Coldwater Indian Band denounces lack of consultation over new Pacific Link pipelineCFJC Today · October 1, 2026
- Cold Lake First Nations seeks judicial review of pipeline designationAPTN News (The Canadian Press) · October 8, 2026
- Don't mistake attendance at a press conference as support for a pipeline, chief saysAPTN News (The Canadian Press) · October 6, 2026
- Mayors, First Nations chiefs in Alberta's oilsands region react tentatively to West Coast pipeline designationCBC News · October 2, 2026
- First Nation seeks say on new Alberta oil pipeline with Metro Vancouver terminalDaily Hive · July 10, 2026
- Canada fast-tracks $44-billion Alberta to B.C. oil pipelineThe Province · October 1, 2026
- One year, one consultation, one decision: overview of the new Building Canada Strong Act (Bill C-39)JFK Law · September 22, 2026
- Bill C-39 (45th Parliament, 1st session)LEGISinfo, Parliament of Canada
- Building Canada Act (S.C. 2025, c. 2, s. 4)Justice Laws Website
About StakeholderHub
StakeholderHub is engagement-records software built in Canada.
This article is general information, not legal advice. It reflects reporting and court records available on October 16, 2026. Nations quoted here speak for themselves; read their statements in full through the sources above.